Poured Concrete Steps

Step-by-step steps: Here's the complete process for laying out, designing and building concrete steps to transition between your patio and a house door.

Intro

Poured concrete steps provide a sturdy, long-lasting transition between an outdoor surface, such as a patio, and the entry to your house. One of the more confusing questions that arises, however, is how high and how deep (front to back) each step should be. The answer to this question is found in some simple math you can use to compute the unit rise and run.

When considering the total run of the unit, local codes often require the top landing to extend at least 12 inches beyond the door swing. Subtract the width of an outswinging door (usually 32 or 36 inches) from the length you measure between the foundation to the outside edge of the steps. If the remainder is less than 12 inches, you may need to change your plan.

Know the codes before you start planning steps. If you don't construct them according to code, a building inspector can make you tear them out. Codes may also have something to say about the placement of rebar or other reinforcements, as well as the concrete mix you use.

Checklist

Time
Two to three days to plan, lay out, and pour three steps (not counting curing time)

Tools
Mason's line, level, framing square, circular saw, hammer, wheelbarrow, mason's hoe, shovel, edger, mason's trowel, broom, lawn sprinkler, tape measure, small sledgehammer, line level, plumb bob, powdered chalk, spade, 4-foot level, tamper

Skills
Designing layout, assembling forms, pouring concrete

Materials
2x lumber, concrete, form-release agent

Get free estimates from local concrete professionals.

Step 1

Measure the rise and run of the site, and drive stakes to indicate where the base of the bottom step will be when poured. Compute the unit rise and run of the steps, and draw a dimensioned sketch.

Step 2

Lay out footings 3 inches wider than the steps. Excavate the footings to the depth codes require, pour the concrete, and insert 12-inch lengths of rebar 7 to 8 inches into the footings. The top of the rebar should be about 2 inches lower than the finished height of the steps. Let the footings cure, then dig a 4-inch trench between them and fill it with tamped gravel.

Get free estimates from local concrete professionals.

Making the Forms: Step 1

Using your plan and the actual dimensions you have computed and sketched, draw the outline of your steps on a sheet of 3/4-inch plywood. Draw the line for the landing so it slopes 1/4 inch per foot. Clamp a second plywood sheet to the first, edges flush, and cut the outline of the step with a jigsaw.

Making the Forms: Step 2

Using a framing square to make sure the forms are perpendicular to the foundation of the house, set the forms in place, and drive supporting stakes alongside them. Make sure the forms are plumb and level with each other, then fasten them to the stakes with 2-inch screws. Cut off any portion of the stakes above the forms.

Get free estimates from local concrete professionals.

Assembling the Forms: Step 1

For each step, cut a piece of 2x lumber to the width of the stairs and rip it to the height of the unit rise if necessary. Bevel the lower edge of each riser (except the bottom one) to make it easier to float the tread when you pour the steps. Fasten the top riser form to the outside of the side forms with three 2-inch screws. Then install the remaining riser forms.

Assembling the Forms: Step 2

Cut angled braces and fasten them to the side forms at the front edge of each step. Then drive 2x4 stakes at the bottom of the braces. Plumb the side forms and fasten the braces to the stakes. To keep the riser forms from bowing, drive a 2x4 stake 18 inches or deeper into the ground in front of the steps. Lay a 2x6 on the risers and fasten it to the stake and to cleats attached to the risers. Attach an expansion strip to the foundation with construction adhesive.

Get free estimates from local concrete professionals.

Filling the Base: Step 1

To save concrete, time, and money, shovel rubble -- clean chunks of broken concrete, river rock, or any clean masonry -- into the space inside the forms. Pile the rubble higher under the landing than the first step, but don't put in so much rubble that it will make the concrete in the steps too thin.

Filling the Base: Step 2

To strengthen the concrete, bend lengths of 1/2-inch rebar so it roughly corresponds to the shape of the rubble mound and lay it on the rubble at 12-inch intervals. Wire perpendicular lengths of rebar across the first pieces. Then raise the rebar up and support it on dobies or balusters that you wire to the rebar.

Pouring the Steps: Step 1

Coat the forms with a release agent. Mix the concrete and bring it to the site in wheelbarrow loads. Shovel the concrete inside the forms, starting with the bottom step and working up. Tap the sides of the forms and risers with a hammer and jab a 2x4 up and down in the mix to drive air bubbles out. Give the concrete enough time to settle between the rubble pieces, and add more concrete if needed.

Pouring the Steps: Step 2

To strengthen the front of each step, cut a section of rebar 4 inches shorter than the width of the step and work it into the concrete about 2 inches behind the riser forms. Then screed the concrete with a 2x4, working from the landing down to the first step. Float the steps from the top down also, working the front edge of the float under the bevel you cut in the riser. Insert J-bolts for your railing, if your railing requires them.

Pouring the Steps: Step 3

Run an edger along the inside edge of each riser form to round the front edge of each step to minimize chipping. If you're going to cover the steps with brick, tile, or stone, leave the edges square.

Pouring the Steps: Step 4

Let the concrete set up long enough to support its own weight, then remove the riser forms and finish the concrete with a trowel. Use a step trowel (a drywall corner knife works as well) to work the corners smooth. Broom the treads to roughen the surface, let the concrete cure, then install the railing. After 12 to 24 hours, remove the side forms and fill in any voids in the concrete.


Comments (0)
8486642707
Add your comment

You must be logged in to leave a comment. Register | Log In
One Hour or Less

Three simple projects to cross off of your to-do list -- just print these instructions and begin!


ADVERTISER